Com­mis­sio­ning of Bel­lin­gen wind farm

We can cele­bra­te our next suc­cess with the com­mis­sio­ning of the Bel­lin­gen wind farm. The pro­duc­tion of the two Ves­tas V162 tur­bi­nes began last Tuesday.

The pro­ject in the Alt­mark regi­on (Sax­o­ny-Anhalt) is loca­ted next to our exis­ting Hüse­litz wind farm.
Once com­mis­sio­ned, the two new plants will sup­p­ly green elec­tri­ci­ty for more than 10,000 house­holds or more than 340,000 elec­tric car char­ges annually.

Spe­cial thanks for the suc­cessful imple­men­ta­ti­on go to the com­pa­nies invol­ved: Ves­tas (tur­bi­ne manu­fac­tu­rer), Max Bögl (foun­da­ti­ons and con­cre­te tower) and FEFA (road and cra­ne sites, cable construction).

Infor­ma­ti­on on the project

Tur­bi­nes
2 x Ves­tas V162 6.2MW (Hub height 166m)

Total power
12.4 MW

Con­s­truc­tion period
April 2024

Contact

+49-5971-8608-55