Rea­li­sa­ti­on of the Bel­lin­gen West wind farm

We are plea­sed to announ­ce that the rea­li­sa­ti­on of our Bel­lin­gen pro­ject is pro­gres­sing successfully.
The cas­ting of the wind tur­bi­ne foun­da­ti­ons was com­ple­ted on sche­du­le so that the sub­se­quent assem­bly of the con­cre­te tower sec­tions can take place.

The pro­ject from the Alt­mark regi­on (Sax­o­ny-Anhalt) is adja­cent to our exis­ting Hüse­litz wind farm.
Once com­mis­sio­ned, the two new plants will sup­p­ly green elec­tri­ci­ty for more than 10,000 house­holds or more than 340,000 elec­tric car char­ges annually.

Spe­cial thanks for the smooth exe­cu­ti­on go to the par­ti­ci­pa­ting com­pa­nies Ves­tas (tur­bi­ne manu­fac­tu­rer), Max Bögl (foun­da­ti­ons and con­cre­te tower) and FEFA (path and cra­ne par­king are­as, foun­da­ti­on civil engineering).

Infor­ma­ti­on on the project

Tur­bi­nes
2 x Ves­tas V162 6.2MW (Hub height 166m)

Total power
12.4 MW

Con­s­truc­tion period
Com­mis­sio­ning plan­ned Janu­ary 2024

 

Pho­tos of the project