Lakiakan­gas 1 + 2

Sin­ce 2011, CPC Fin­land Oy, a whol­ly owned sub­si­dia­ry of CPC Ger­ma­nia GmbH & Co. KG, has been deve­lo­ping onshore wind farm pro­jects in Finland.

With the com­mis­sio­ning of the two wind farms Lakiakan­gas 1 (6.9 MW in 2017) and Lakiakan­gas 2 (50.4 MW in 2019), CPC Fin­land Oy will reach a total instal­led capa­ci­ty of 57.3 MW. Thus, the suc­cessful imple­men­ta­ti­on, with over 400 MW strong, alre­a­dy appro­ved port­fo­lio, has begun.

The elec­tri­ci­ty gene­ra­ted by the flag­ship Lakiakan­gas 2 pro­ject will be purcha­sed on a long-term basis through the first Fin­nish PPA (power purcha­se agree­ment) with Google.

The pro­ject was finan­ced and rea­li­zed wit­hout govern­ment sub­si­dies and was imple­men­ted and put into ope­ra­ti­on within only twel­ve months after the finan­cing was completed.

YouTube

Mit dem Laden des Videos akzeptieren Sie die Datenschutzerklärung von YouTube.
Mehr erfahren

Video laden

Project posts

There are no posts on this project.

Information

Turbines

2 x Ves­tas V126 – 3.45 MW
12 x Ves­tas V150 – 4.2 MW

Total power

57.3 MW

Construction period

2016–2019

Contact person

Erik Trast
Gene­ral Manager