Roteberg

Since the beginning of 2019, the Roteberg wind farm has been successfully supplying green electricity to the public grid. The commissioning was long awaited for all of us. Even the start of construction could only take place later than originally planned. The reason for this was that the access road and the cable route envisaged in the planning could not be realized in this form. With the completion of extensive and intensive replanning, construction work could finally start in mid-2018.

Following the successful installation of a total of five modern wind turbines of the 3.45 MW class, we as the operator of the Roteberg wind farm, together with the owners, are looking forward to the future with great expectations.

Contributions to the project

There are no contributions to this project.

Information

Turbines/modules

5 x Vestas V117/141.5m - 3.45 MW

Total power

17.25 MW

Construction Period

2017-2018