Knip­pen

The wind farm on the Knip­pen to the nor­the­ast of the town of Freu­den­berg con­sists of three tur­bi­nes of the type N117‑2.4MW from the manu­fac­tu­rer Nordex.

Our pro­ject imple­men­ta­ti­on sche­du­le was post­po­ned several times due to a lawsu­it filed by a local resi­dent. Nevertheless, manu­fac­tu­rers, land owners, par­ti­ci­pa­ting com­pa­nies and we our­sel­ves belie­ved in the suc­cess of the pro­ject and stuck to the Knip­pen wind farm.

The delay signi­fi­cant­ly incre­a­sed expen­ses for unfo­re­se­en addi­tio­nal cos­ts, so that the bud­get could not be met. Through the coope­ra­ti­on of the main land owner as well as the manu­fac­tu­rer, fixed cos­ts could be redu­ced and thus the Knip­pen wind farm could be realized.

With the goal of theo­re­ti­cal­ly being able to sup­ply the ent­i­re popu­la­ti­on of the town of Freu­den­berg with green and clean electri­ci­ty with the three wind tur­bi­nes, the pro­ject ulti­mate­ly did suc­cess­ful­ly go into ope­ra­ti­on in July 2018.

Project posts

There are no posts on this project.

Information

Turbines

3 x Nordex N117/141m – 2.4 MW 

Total power

7.2 MW

Construction period

2016–2018